The Village of Elba is continuing a major, multi-phase improvement project at the Village Wastewater Treatment Facility (WWTF) and sanitary sewer system. The approximately $5 million project represents an important investment in infrastructure that serves Village residents and businesses every day.
The last major upgrade to the Wastewater Treatment Facility occurred in 1981. Over the past 45 years, the facility has continued to operate with relatively few major improvements, and the treatment lagoons have not undergone a significant sludge removal project since that time. The current project is intended to modernize aging equipment, improve reliability and energy efficiency, reduce unwanted groundwater and stormwater entering the sanitary sewer system, and position the Village for many years of continued service.
The improvements have been divided into three phases.
Phase 1 – Wastewater Treatment Facility Improvements – COMPLETE
Phase 1 included the installation of a new ultraviolet (UV) disinfection system, replacement of the facility’s effluent pumps, and installation of a new backup generator for the Wastewater Treatment Facility. These improvements provide more reliable treatment and disinfection while improving the facility’s ability to continue operating during power outages.
Phase 3 – Sanitary Sewer Collection System Improvements – COMPLETE
Phase 3 focused on reducing inflow and infiltration (I&I) within the Village sanitary sewer system. I&I occurs when groundwater or stormwater enters sanitary sewers through cracks, deteriorated pipes, leaking joints and manholes. This additional water unnecessarily consumes treatment capacity at the WWTF. Improvements included spot sewer repairs, trenchless sewer pipe relining, and rehabilitation of sanitary sewer manholes. Reducing I&I helps extend the useful life of the collection and treatment systems and reduces the amount of unnecessary water that must be pumped and treated.
Phase 2 – Lagoon and Aeration System Improvements – CURRENTLY UNDER CONSTRUCTION
Phase 2 is currently approximately 30% complete and represents the final major component of the overall project. Work includes replacing the existing blowers with new, more energy-efficient equipment, electrical upgrades, installing new air piping and aeration equipment within the treatment lagoons, and removing decades of accumulated sludge from the lagoons. Phase 2 also includes installation of permanent backup generators at both Village sanitary sewer lift stations, improving the reliability of the collection system during power outages.
Removal of the accumulated lagoon sludge is necessary for the new aeration equipment to operate properly and efficiently. Once completed, the project will restore lagoon capacity and provide a treatment system that should not require another major sludge removal project for many decades. The new blowers and aeration equipment are also expected to provide long-term electrical and operational savings for the Village.
Unanticipated Sludge Quantities and Additional Funding
During construction, the Village discovered that the amount of accumulated sludge within the lagoons is significantly greater than originally estimated. With approximately 45 years of sludge accumulation, determining the exact quantity prior to removal was difficult.
The additional sludge must be properly removed, dewatered, transported and disposed of at an approved facility. The substantially greater quantity has resulted in an unanticipated project cost increase. To complete this necessary work, the Village anticipates borrowing approximately $725,000 in additional funds.
The Village recognizes that borrowing additional money is not ideal and understands the concern that comes with any increase in project costs. However, completing the sludge removal is necessary for the new aeration system to function as designed and for the Village to realize the full benefit of the improvements already underway. Deferring the work would leave a known operational issue unresolved and would likely result in additional costs in the future.
The Wastewater Treatment Facility is a vital piece of Village infrastructure that operates every day to protect public health and the environment. Just like roads, water systems and other essential infrastructure, the WWTF must be maintained and periodically upgraded to remain reliable, efficient and compliant with current requirements. With the last major facility improvements dating back to 1981, this project represents a long-term investment that was necessary to keep the system functioning effectively for future generations.
A Long-Term Investment in the Village
The Village has been successful in obtaining more than $3.3 million in grant funding toward the approximately $5 million wastewater improvement program. This funding substantially reduces the amount of project costs that must ultimately be borne by Village sewer users.
The Village has historically taken a fiscally responsible approach to managing its infrastructure and finances and remains committed to making decisions that balance the immediate financial impact on residents with the long-term needs of the community. While the additional borrowing is an unexpected and difficult component of the project, completing the work now is considered the most responsible approach to protecting the significant investment already made in the wastewater system.
When all three phases are complete, the Village will have a modernized wastewater system with improved treatment equipment, reliable emergency power, reduced I&I, rehabilitated sewers and manholes, restored lagoon capacity, and more energy-efficient aeration equipment. The improvements are expected to reduce electrical consumption and operating costs while helping minimize the need for another major lagoon sludge removal project for many decades.
Ultimately, this project is about protecting an essential Village asset and ensuring that Elba has a reliable and efficient wastewater system for decades to come, while continuing the Village’s commitment to responsible stewardship of residents’ funds.